ISTech Support Forum
http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Suggestions for Updates >> Recalc WO Estimated Costs http://www.istechforum.com/YaBB.pl?num=1099138977 Message started by kgenco on 10/30/04 at 04:22:57 |
Title: Recalc WO Estimated Costs Post by kgenco on 10/30/04 at 04:22:57 After swapping substitutes, there is no automatic recalculation of the estimated costs for the workorder. You have to go into WO-A and then manually recalc costs causing a significant amount of extra time. There are occasions when we may need to swap subs on 50-100 workorders at a time based upon availability of items. A feature to recalc after swapping would be greatly appreciated and a global recalc estimated costs (similar to WO-K-H) would be nice to catch all the ones that may have been missed up until now. |
ISTech Support Forum » Powered by YaBB 2.1! YaBB © 2000-2005. All Rights Reserved. |