http://www.istechforum.com/YaBB.pl Evo-ERP and DBA Classic >> Suggestions for Updates >> IN-B Sources - Require / Alert No Vendor - R Type http://www.istechforum.com/YaBB.pl?num=1180112127 Message started by cpitta on 05/25/07 at 09:55:27 |
Title: IN-B Sources - Require / Alert No Vendor - R Type Post by cpitta on 05/25/07 at 09:55:27 A short time ago we began to impliment WO - Q (Convert WO to PO) to streamline our purchasing process. Part of the WO to PO process requires type R items to have a vendor set up at the item level (IN-B). We are running into issues where those entering new type R items are not always entering a supplier - which defeats the purpose of using the WO to PO process. It would be great to have at the minimum a warning that alerts a user that they have not entered a vendor for an R type item - ideally I would like it to be required that a vendor is entered for all R type items. Christina |
Title: Re: IN-B Sources - Require / Alert No Vendor - R T Post by Dick on 06/07/07 at 07:22:02 MR-H (?plus other MR-'s?) is the same - no vendor, not report . I have "?" vendor for temporary use. Either requiring a vendor in IN-B or allowing the routines to function / report with a blank vendor would work for me. Dick |
Title: Re: IN-B Sources - Require / Alert No Vendor - R T Post by Theran on 06/20/07 at 18:29:04 How do you get WO-Q? I don't have it as a menu choice. I looked in SD-Q in the MFG tab and don't see a way to turn this feature on. I am on DBA V2004.1 with IS Tech Support Update 5/1/07. What am I missing? |
Title: Re: IN-B Sources - Require / Alert No Vendor - R T Post by Theran on 06/20/07 at 19:02:20 By the way, I did check PS-B to make sure I had menu access. There is a Y under the Q column for Work Orders. |
Title: Re: IN-B Sources - Require / Alert No Vendor - R T Post by Lynn_Pantic on 06/20/07 at 19:17:47 Convert WO to PO is an add-on that cpitta has purchased that converts all type R parts on WO BOM to PO if they are not available in stock. |
Title: Re: IN-B Sources - Require / Alert No Vendor - R T Post by cpitta on 06/21/07 at 09:20:57 We do almost all of our purchasing for specific jobs; and therefore, on our POs we line item dedicate each item to a specific job work order. The WO to PO conversion works great! (when preferred suppliers are set up for all the R type items on the BOM). It reduces the amount of time purchasing takes to produce POs from BOMs. Also, it can automatically apply any R type items that may be in stock to the job. |