Welcome, Guest. Please Login.
11/01/24 at 19:27:03
News:
Home Help Search Login


Pages: 1
Send Topic Print
WO-P Batch Finished Production (Read 341 times)
Mike_Vader
Ex Member



WO-P Batch Finished Production
02/03/04 at 11:43:46
 
Would it be possible to have a summary report added for this that would give us the actual cost for each work order and the expected(Standard) cost for each work order?
 
Previously we could see this as the work orders were flushed individually (though it was quite tedious).
 
It would be even better if this summary report was printable. So we could keep a record of the job costing for all orders flushed each day.   Roll Eyes
Back to top
 
 
  IP Logged
Lynn_Pantic
Administrator
*****


evolution (n) -
gradual change to a
different form

Posts: 5681
Re: WO-P Batch Finished Production
Reply #1 - 02/03/04 at 11:55:50
 
IN-N-A for type W transactions for a date range should give you what you are looking for.  It can be run in detail or summary mode.
Back to top
 
 

Lynn Pantic
IS Tech Support
lynn@istechsupport.com
Email   IP Logged
Mike_Vader
Ex Member



Re: WO-P Batch Finished Production
Reply #2 - 02/03/04 at 12:04:58
 
Hi Lynn,
 
That looks like it should work actually.
 
thanks,
 
Mike
Back to top
 
 
  IP Logged
Pages: 1
Send Topic Print