On of the problems we have with MRP is that some of our costliest items are used at the end of our production of an end item and whole process can take up to a month.
We tie all of our items to sequences. Will there ever be a way to drive the MRP using WO sequence start dates instead of WO start dates?
If I'm dreaming, just wake me up -- I'll get over it.